Work in progress:
- Completed AHU #3 duct tie-in to AHU #2.
 - Air handler unit #3 has been permanently shutdown.
 - Start layout for tele/data ductbanks.
 - Starting motor control center (MCC) and swithgear duct bank.
 - Started mass excavation - currently 95% complete. Shoring and lagging is now complete.
 - Installing exterior scaffolding to 3rd floor on the west side of the building inside the construction fence.
 - Phoenix air valve replacement in the Annex research labs continues per schedule.
 
Looking ahead for next week:
- Start demolition of AHU #3.
 - Continue chilled water piping in 3rd floor east mechanical room.
 - Complete the 10" water line relocation.
 - Continue abatement of 3rd floor west mechanical room.
 - Start prep work for abatement in 3rd floor east mechanical room.
 - Start electrical service from MCC to new AHU #1 in the 3rd floor east mechanical room.
 - Continue Phoenix air valve replacement in the Annex.