Work in Progress:
- CMU wall in the receiving and student machine shop is complete.
 - Working on electrical raceways on the second floor.
 - Completed demolition on the second floor.
 
Looking ahead:
- Carpenters to start layout & framing on Monday in 101 & 104, 223 and machine shop.
 - Vent/beam patching from old uni-vents will start next week.
 - Pour slab on grade weather permitting next week.
 - Continue electrical rough-in on first and second floors.
 - Begin demolition of third floor lab for restroom renovation.