Work in Progress:
- Phoenix air valve replacement in the Annex research labs continues per schedule.
 - Continuing the chilled water piping in the 3rd floor east mechanical room.
 - Continuing the demolition of AHU#3.
 
Looking forward:
- Complete the demolition of AHU#3 in the 3rd floor west mechanical room.
 - Mobilize the mason the week of 3/7/2016.
 - Continue Phoenix air valve replacement in the Annex.
 - Continue chilled water piping in the 3rd floor east mechanical room.
 - Steel submittals and manufacturing in progress.
 - Start tele/data duct bank layout.
 - Start excavation for footers and layout for basement foundation walls.