Work in Progress:
- Wall layout and coordination has begun in rooms 101 & 104, 223 and machine shop.
 - Plumbing trenches in 101 & 104 have been backfilled and prepared for floor slab pour.
 - Underground plumbing rough-in was inspected and approved on 2/24/16.
 
Looking ahead:
- Pour floor slab in fills in 101 & 104 on 2/26/16.
 - Pour floor slab in new first floor restroom on 2/26/16.
 - Start framing 101, 104, 223 and machine shop.
 - Plumbing rough-in in new first floor restroom will begin.
 - Electrical rough-in following metal stud framing on first and second floors.
 - Facing brick masonry will continue at the addition weather permitting.