Work in Progress:
- Continuing the steam and condensation piping in the East Mechanical room.
 - Heating and snow melt piping is continuing in the West Mechanical room.
 - Continuing with the chilled water piping in the West mechanical room.
 - Working on plenum duct at AHU-1 in East Mechanical Room.
 - Currently working on fiber data backbone.
 - Currently installing cable tray in tunnel.
 - Waterproofing of south wall continues.
 - CMU and elevator hoistway has begun.
 
Looking Forward:
- Final connections to coils and control valves for new AHU-1 in East Mechanical room.
 - Continue chilled water piping in West Mechanical room.
 - Install new roof exhaust curbs.
 - Begin startup of AHU-1 and commissioning.
 - Complete 1st and 2nd floor lab demolition.
 - Complete with stair demolition.
 - Form and pour the west wall on 4/25-4/27.
 - Complete the elevator hoistway.
 - Vac truck to remove the roof ballast from the Cunningham Annex roof on 4/23-4/24
 - Roofing material delivery on 4/26, roofing to start on 4/27.