Work in Progress:
- Completed first lift pour for elevator #2 (South).
 - Completed first lift pour for stair tower #3.
 - Grade beams and pile caps along column line 17 are complete.
 - Steel clips for sequence 1-4 are complete.
 - Steel erection for sequence 1-4 is in progress.
 
Looking forward:
- Continue with the installation of the steel erection of sequences 1-4.
 - Form and pour lift #2 for elevator #2 (south).
 - Pour concrete basement retaining wall from column line 16 to 17B.
 - Pour pile caps and grade beams along column line G.
 - Interior caps and grade beams along columns 9, 11, and 13 between A and C.
 - Form concrete basement retaining wall from 17B to 17C.