Work in Progress:
- Currently installing 1J electric panel, wire and raceways. Confirmed an electric shutdown will not be required now.
 - Continuing to pull wire throughout.
 - Continuing with HVAC sheet metal duct work on the 1st and second floor.
 - Completing domestic water piping rough-in for drywall boarding.
 - Framing continues for stairwell partitions.
 - Steel erection is substantially complete.
 
Looking Forward:
- Cut masonry opening for AHU penetrations in south wall.
 - In-fill window openings with masonry at AHU location on the second floor.
 - AHU Curb delivery scheduled for 4/27.
 - Remaining demolition and abatement of tile work schedule for week of 4/25.
 - 3rd floor HVAC work to start week of 4/25.
 - Drywall and taping throughout building.