9/26- Williams Hall/ISB Construction Updates
	
 
  
    
  
          
            ISB
Work in Progress
	- Continue the work of water proofing mud mat on the east side of the building, lines 14 to 17.
 
	- Continue framing roof work at east side of the building, and roofing work on the penthouse.
 
	- Continue curtain wall installation at the northeast side.
 
	- Continue backfilling for slab on grade from line 7 to 17.
 
	- Continue pre cast and brick work along A line.
 
	- Continue brick work along line 17, from B to G.
 
	- Continue miscellaneous detailing work.
 
	- Start Hydraulic slab on the east side, lines 14 to 17.
 
	- Start retaining wall along line 8.
 
	- Finalize concrete work for stair #3.
 
Looking Forward
	- Continue pre cast and brick work along line 17, from B to G.
 
	- Pour retaining wall along line 8.
 
	- Pour Hydraulic slab on the east side of the building, lines 14 to 17.
 
	- Start installation of the CMU in penthouse.
 
	- Start backfilling for slab on grade, east side of the building, lines 14 to 17.
 
	- Finalize pre cast and brick work along line A.
 
Williams Hall
Work in Progress
	- Piping work for steam station in mechanical room is in progress.
 
	- Continue ductwork installation on the east side of the building, 1st floor and 2nd floor from lines 1 to 17.
 
	- Continue plumbing work for W3.
 
	- Continue electric rough installation in basement.
 
	- Continue final painting concrete.
 
	- Start tapping drywall for W3.
 
	- Installation of steel for exhaust fans on roof for W3 has begun.
 
	- Finalize concrete repair work.
 
Looking Forward
	- Continue piping work for steam station in mechanical room.
 
	- Continue ductwork installation on the east side of the building, 1st floor and 2nd floor from lines 1 to 17.
 
	- Continue plumbing work for W3.
 
	- Continue electric rough installation in basement.
 
	- Continue final painting concrete.
 
	- Continue curtain wall installation.
 
	- Start priming drywalls for W3.
 
	- Start installation of mill work for W3.
 
	- Start fireproofing in penthouse and 2nd floor on the east side of the building.
 
 
      
    
    
 